Years | 2000 | 2001 | 2002 | 2003 | 2004-2006 | 2007 | 2008 | 2009 | 2010 | 2011 |
---|---|---|---|---|---|---|---|---|---|---|
Case study data collection | X | |||||||||
New CEO hired | X | |||||||||
Introduction of Lean | X | |||||||||
Senior-level staff, managers trained on Lean principles | X | X | X | X | ||||||
Other QI methods reviewed by CEO | X | X | X | |||||||
Lean initiatives underway | X | X | X | X | X | X | X | |||
UTI Project Selection | X | |||||||||
E-Prescribe Project Selection | X |
Note: Shading in a cell, denoted here by an X, indicates that the relevant activity (row) commenced or continued during the time period (column).